TCC Northwest Bond Project Update for October/November 2020

The Connect4 web series, hosted by project development and construction group Skanska, was held during October and November to provide TCC Northwest bond project updates.

TCC Northwest Project Updates

Project Highlights

  • 100% of Phase I contracts were awarded; 50% of which were awarded to MWBE firms.

Phase II and III Bids

Phase II bid opportunities took place in November 2020.

The major trades and scopes for Phase II and III bidding focus on utilities, civil/earthwork, underground infrastructure and electrical.

The major trades and scopes available for Phase II and III bidding are:

  • Building pads
  • Chem inject/moisture
  • CHW/Thermal piping
  • Clear and grub
  • Concrete washout
  • Demolition hardscape
  • Demolition landscape
  • Demolition utilities
  • Domestic water
  • Fire water
  • Gas
  • Grading
  • Lime stabilization
  • Patch and repair concrete
  • Rock excavation per Geo Tech
  • Sanitary sewer
  • Spoils
  • Stockpile spoils
  • Storm drain
  • Street sweeper
  • SWPPS
  • Wheel wash stations

Timelines

Skanska provided next steps and an updated timeline for the project.

  • November 2020: Phase II bidding
  • February 2021: Open Phase III bidding